Technical conclusion on the examination of the building sample. Example of imprisonment of buildings

According to the results of the examination of building structures, a report on the technical condition of the building structures (facilities) is drawn up.
In accordance with GOST 31937-2011 "Buildings and structures. The rules of examination and monitoring of the technical condition" There are 4 categories of the technical condition of building structures:

  • Regulatory technical condition.
  • Workable technical condition.
  • Limited workable technical condition.
  • Emergency condition.

What is included in the technical report resulting from a building survey:

Technical Report on the results of the building survey

Report technical examination It consists of textual part, photos, graphic material and applications, and contains the following sections:

1. Title List

Title list includes

full name of the reporting document,

the name of the object of the survey and its location,

name of a specialized organization that performs work and

evidence number SRO with admission to this species works,

the year of work performed, approval by the head of a specialized organization.

2. Introduction

The "Introduction" section contains:

2.1. justification, information about the organization conducted by technical inspection; data about the customer; data on the operating organization;

2.2. Copies of documents for the right to conduct work

2.3. The technical task is to be coordinated with the customer, it is spelled out all the goals and objectives of the survey;

2.4. The survey program is coordinated with the Customer, it describes the stages of work on the survey;

2.5. Steering Scientific and Technical Documentation - List of Gostov, SP and SNIPs used during examination;

2.6. The composition of specialists - a list of specialists who produced surveys and their qualifications;

2.7. List of instruments and equipment - with information about the verification of these devices and equipment.

3. Analysis of technical documentation

The "Analysis of Technical Documentation" section provides data on the presence / absence of design technical documentation for this building (construction), information about the project, construction organizations, Passports BTI, the results of previous surveys, etc.

4. Results of the examination of structures

4.1. General Data on Survey

The section provides a description of the stages of work:

preliminary (visual) examination

detailed (instrumental) examination,

as well as a description of the composition of work.

4.2. Results of the visual examination of building structures

The section describes building structures of the building (facilities), defects and damage are detected, a preliminary assessment of the technical condition of building structures is given.

4.3. The results of the visual survey of engineering networks

The section describes those present in the building. network engineering, their defects and damage to external features are detected.

4.4. Results of a detailed (instrumental) survey

This section provides:

1) the actual dimensions between the axes of the main structural elements: spans, steps of columns, height mark, distance between nodes;

2) plans for her, cuts, facades, roof plan;

3) deviations of the overall dimensions of the cross section and the lengths of the structural elements from the project;

4) the actual strength characteristics of the main building materials;

5) Defects and damage to the elements, nodes and schemes of their location (defective statement is drawn up with the need to count the volumes of repair and restoration work).
Depending on the type of building constructions, GOST provides for a certain number of works, which in each case are determined by the objectives and tasks of the survey and may differ from the above list.

6) conclusions with a brief presentation descriptions of identified defects and damage, causes of their appearance;

7) the conclusion of a technical examination of the building (facilities);

8) Recommendations to eliminate the identified defects. Recommended measures to enhance structures, eliminate defects and damage, and bring them in line with the requirements of NTD.

4.5. Results of test calculations

The section provides the results of completed test calculations of structures and their elements.

4.6. Roll control and precipitate

If the visual examination shows the deflection, rolls, precipitation, etc., then this section provides information on the results of the measurements of these defects with geodesic devices.

5. Extract from GOST 31937-2011 "Buildings and structures. Rules of examination and monitoring of the technical condition"

The section provides an extract from GOST with a list of categories of the technical condition of building structures.

6. Conclusion about the technical condition of building structures

It is drawn up on the mandatory application of G GOST 31937-2011 "Buildings and structures. Rules of examination and monitoring of the technical condition."

The section provides an assessment of the technical condition of building structures with the substantiation of the assigned category of technical condition.

Also in the section contains recommendations to eliminate the identified defects and damages, recommended measures to strengthen structures, eliminate defects and damage, and bring them in line with the requirements of NTD.

With a limited operational or emergency condition of the object, a task is prepared for designing measures to restore or enhancing structures.

7. Applications:

7.1. Photographing results
The section provides photographs of facades, roofs, indoor premises of buildings, defects and damage, shruffs and opening designs.

7.2. Copies of qualifying certificates

7.3. Copy of software licenses used in calibration calculations

7.4. Graphic materials

The section provides the results of natural measurements of the foundations in shurs, floor plans, characteristic cuts, measurement schemes, location schemes of defects, facades drawings, etc. Depending on the purposes and objectives of the survey.

The technical report with the conclusion of the technical condition of buildings (structures) is signed by persons who conducted a technical inspection, approved by the head of a specialized organization.

According to the results of technical inspection of buildings (structures), measures are being developed to eliminate the identified deviations from the requirements of regulatory and technical documents, safety requirements and bringing the building (facilities) into an efficient state.

Engineering and technical center "Quality" provides services for the examination of buildings, structures and designs with the execution of a full technical report.

Buildings section number 1.
The right to carry out this type of work is confirmed by a certificate of admission.
The survey is caused by the need to evaluate the technical condition of the building structures due to the existing deformations of the structural elements.
The design documentation for the examination of the building structures includes the following types of work:
- Perform measurement work to determine the parameters of the structural elements of the building;
- assessment of the actual technical condition of the main supporting structures and the building as a whole;
- issuance of recommendations to ensure the further operational suitability of the building.

Based on the results of the survey conducted in accordance with the requirements
SP 13-102-2003 and GOST 53778-2010, a present report compiled, including:
- Drawings of the building (plans, cuts, facades);
- results of the examination of structures (walls, overlapping, coatings, structural elements) with the photo application of the existing defects;
- conclusions to assess the technical condition of the structures;
- Recommendations to ensure the further normal operation of the building.
When performing work, the following documentation was used:
1. Technical certificate on a warehouse building.
2. Fragment of topographic shooting site of the building.

2.2. a brief description of Object
2.2.1. common data

The surveyed building is located in Rostov-on-Don.
Climatic conditions:
- climate district - III B;
- Calculated winter temperature - 220 s;
- the calculated snow load for the II of the Snow Area (by SNiP 2.01.07-85 *) on the horizontal projection of the roof - 1.20 kPa;
- normative high-speed wind pressure for the III area (by SNiP 2.01.07-85 *) at height before10 m - 0.38 kPa;
- the regulatory depth of the primerization of the soils (SNIP 2.02.01-83) - 0.9 m;
- Seismicity of the area - 6 points.
Characteristic of the building:
- the level of responsibility of the building is normal;
- the degree of durability - II;
- degree of fire resistance of the building - II;
- class on functional fire danger - F 1.1.
Technical and economic indicators:
Total area - 687.8 m2.
Building volume - 2313 m3.

2.2.2. Terms of construction and operation of the building

The warehouse building was built in 1966. Information about previous building surveys, as well as the preserved documentation for the construction of the building is absent.
From the words of employees who operate the building, several years ago, for a long time, soaked sorates of the foundations of the foundations by the waters of hot water supply (in the area of \u200b\u200bthe axis "2").
During the examination, it was noted that part of the building in the axes "1" - "2" was attached later by the main building.
In the immediate vicinity of the "5" axis of the building of the building is located neighboring.
When viewing the building, elevated humidity and dampness in the basement premises were noted.

2.2.3. Surgical Planning and Design Solutions

The building is a single-storey brick, rectangular shape in terms of shared sizes in the axes of 37.3x11.7 m. For a part of the building in the 2/1 axes - "4" is located a basement with a height of 2.4 m. The height of the first floor is 3.7 ... 3.8 m.
Constructive building scheme - frameless with carrier brick longitudinal walls.
Foundations - tapes on a natural base.
Overlapping basement - reinforced concrete plates.
Coating - reinforced concrete ribbed and crowded plates.
The beam, which relieves the slabs of the overlap in the axes "1" - "2" - metal.
Jumpers over window openings are metallic.
Roofing - from roll-up materials.
Plans, cuts and facades are shown on sheets of graphic part and in photosappendix 4.1.

2.3. Examination of structures

2.3.1. Foundations and engineering and geological conditions

During the inspection of the building, the foundations were not revealed and not studied.
There are no data on engineering and geological surveys. Relief plot calm, flat.

2.3.2. Walls and jumpers

Materials of walls and jumpers
The walls of the building are made of ceramic brick. The surface of the walls in the premises of plastered. The thickness of the external I. inland walls It is 440 mm with a plaster layer. M100 brick brand.
In the premises of the basement and the first floor there are partitions with a thickness of 150 ... 300 mm of bricks.The thickness of the walls of the building does not meet the requirements of the norms on heat engineering.
Wall and Jumper Defects
The main defect of the building walls is vertical, inclined and horizontal cracks of sedimentary character. The width of the disclosure of cracks in the walls of the building is up to 15 mm. Maximum deformations are marked in the axes "1" - "3".
Jumpers over the opening of the building are made metal from the Corner L75x75 and Schawler)